EP146C How do I estimate resources accurately?

Accurate resource estimation is critical for project success. Poor estimation can lead to delays, budget overruns, overworked teams, and even project failure. Here’s how to accurately estimate resources and the risks of getting it wrong.


1. Identify Project Requirements

πŸ”Ή Start by breaking down the project into tasks and deliverables.
πŸ”Ή Identify the type of resources needed, such as:

  • Human Resources (employees, contractors, specialists)
  • Material Resources (equipment, software, tools)
  • Financial Resources (budgets, funding, investments)
  • Time Resources (man-hours, project duration)

πŸ“Œ Example: If developing a mobile app, you need developers, designers, testers, and software licensesβ€”all of which must be accounted for.


SIX FIGURE OPPORTUNITY!!

HIGH INCOME, NO DEGREE REQUIRED

Taught by Nick, whose experience is well documented in the International Business Times and The Source magazines, this course gives you all the training you need to start in this very sought after career. Through flexible online learning and then 1-to-1 tuition, you are guided through the theory of project management and then shown how to get your first job. The generous 14 day refund policy is guaranteed at the checkout.

2. Use Data from Past Projects

πŸ”Ή Analyze previous projects of a similar scope to estimate resources.
πŸ”Ή Use historical data to determine average time, cost, and effort required.
πŸ”Ή If no past data exists, consult industry benchmarks or seek expert opinions.

πŸ“Œ Example: If a previous marketing campaign took six weeks and required five team members, use that as a baseline while adjusting for project differences.


3. Break Tasks into Smaller Units

πŸ”Ή Use Work Breakdown Structure (WBS) to divide the project into smaller, manageable tasks.
πŸ”Ή Assign estimated resources to each task rather than the entire project at once.
πŸ”Ή Ensure dependencies are identified to avoid bottlenecks.

πŸ“Œ Example: If designing a new website, break the project into UI design, backend development, content creation, and testingβ€”estimating resources for each phase separately.


4. Consider Availability and Productivity

πŸ”Ή Account for team availability, including vacations, sick leave, and working hours.
πŸ”Ή Factor in realistic productivity levelsβ€”employees rarely work at 100% efficiency all the time.
πŸ”Ή Include a buffer (10–20%) for unexpected delays or slowdowns.

πŸ“Œ Example: If a software engineer typically writes 500 lines of code per day, estimate 400 lines to allow room for testing and debugging.


5. Use Estimation Techniques

πŸ”Ή Bottom-up Estimating – Estimate resources for small tasks and add them up.
πŸ”Ή Top-down Estimating – Use a high-level estimate based on past projects.
πŸ”Ή Three-Point Estimation – Calculate using:

  • Optimistic Estimate (O)
  • Most Likely Estimate (M)
  • Pessimistic Estimate (P)
  • Formula: (O+4M+P)/6(O + 4M + P) / 6

πŸ“Œ Example: If an IT upgrade could take 2 weeks (optimistic), 3 weeks (most likely), or 5 weeks (pessimistic), the estimated time is (2 + 4(3) + 5) / 6 = 3.16 weeks.


SIX FIGURE OPPORTUNITY!!

HIGH INCOME, NO DEGREE REQUIRED

Taught by Nick, whose experience is well documented in the International Business Times and The Source magazines, this course gives you all the training you need to start in this very sought after career. Through flexible online learning and then 1-to-1 tuition, you are guided through the theory of project management and then shown how to get your first job. The generous 14 day refund policy is guaranteed at the checkout.

6. Monitor and Adjust Estimates

πŸ”Ή Track actual resource usage as the project progresses.
πŸ”Ή Compare against initial estimates and adjust allocations if necessary.
πŸ”Ή Maintain flexibility to adapt to unforeseen issues.

πŸ“Œ Example: If a construction project faces delays due to bad weather, reallocate teams to indoor tasks temporarily.


Consequences of Inaccurate Resource Estimation

1️⃣ Project Delays – Underestimating resources leads to slow progress and missed deadlines.
πŸ“Œ Example: The Sydney Opera House (originally planned for 4 years) took 14 years due to poor planning and underestimations.

2️⃣ Budget Overruns – Underestimating costs leads to financial strain or incomplete projects.
πŸ“Œ Example: The Denver International Airport automated baggage system ran $560 million over budget due to underestimated technical complexity.

3️⃣ Overworked Teams – Insufficient staffing can cause burnout, decreased productivity, and resignations.
πŸ“Œ Example: In game development, “crunch time” occurs when teams work excessive overtime due to poor planning, leading to high turnover.

4️⃣ Resource Shortages – Underestimating materials or tools can halt progress.
πŸ“Œ Example: A manufacturing company miscalculated raw material needs, causing a production delay that lost major clients.


Conclusion

Accurate resource estimation requires detailed planning, historical data, structured techniques, and continuous monitoring. Getting it wrong can lead to delays, financial losses, and operational failure, so it’s essential to estimate wisely and stay adaptable. πŸš€

SIX FIGURE OPPORTUNITY!!

HIGH INCOME, NO DEGREE REQUIRED

Taught by Nick, whose experience is well documented in the International Business Times and The Source magazines, this course gives you all the training you need to start in this very sought after career. Through flexible online learning and then 1-to-1 tuition, you are guided through the theory of project management and then shown how to get your first job. The generous 14 day refund policy is guaranteed at the checkout.